INTREC were engaged by Maryvale Private Hospital to deliver complex multi-staged construction and refurbishment within a live hospital.

The project consists of three new Operating Theatres, a new Central Sterile Supply Department, 19 new patient recovery bays, a new nurse station, the installation of Reverse Osmosis systems, an extension to the Hospital secure parking and the construction of a new fire ring main supplied by two 90,000L water tanks.

The project consists of two new operating and one refurbishment of an existing operating room, 19 new patient recovery bays, a new nurse station, the installation of reverse osmosis systems and an extension to the Hospital’s secure parking.

Project risks include service interruptions and change overs for new distribution switchboard works. Disruptions to Hospital Staff and Patients. Impacts on Supply Chain due to COVID-19. Infection Control with existing live hospital environments. Subcontractor/Supplier Project Withdrawal. Airborne dust management. Coordination of client-supplied and installed specialist equipment. Installation of medical pendants. Regional project management. Commissioning of hospital equipment.

INTREC’s successful onsite management ensured the early scope of works was performed without disrupting the hospital’s daily activity. These activities included the construction of temporary access roads, various crane lifts, 158m3 of concrete poured, and non-destructive civil digging.